2 years behind schedule, the Pattullo Bridge replacement nears completion

Province says $1.637-billion project expected to open in fall 2025, after years of delays

CBC News

An 80-metre gap is all that separates the main bridge deck from the north ramp of B.C.'s Pattullo Bridge replacement. High above the Fraser River, construction crews work to connect the two sides, one rebar at a time.

The space may look vast, but engineer Wendy Itagawa says it's a relatively small section of the bridge's 1,200-metre length.

"We're getting really close now," said Itagawa, who is the executive director of the Pattullo Bridge Replacement Project. "We're installing the cables and the…

Continued...

Read the full story on the CBC website

2 years behind schedule, the Pattullo Bridge replacement nears completion

SOURCE www.cbc.ca

Posted by
Share your news and events for free on lokol Surrey
SHOW ME HOW


11
https://surrey.lokol.me/s/2-years-behind-schedule-the-pattullo-bridge-replacement-nears-completion-62460-10348520
CBC News, Posted: Jun 20, 2025 10:00 AM EDT | Last Updated: 17 minutes ago
Living News From Local Media

0

Log In or Sign Up to add a comment.
Depth
seek-warrow-w
  • 1
arrow-eseek-eNo items to display
View all the LATEST
and HOTTEST posts
View

Share this comment by copying the direct link.

  • Our
    Sponsors

Using this website is subject to the Terms of Use that contain binding contractual terms.